Progress to date

Table 1: Project Progress to date – November 2023

Project Name Project No. Current Progress to date (%) Expected Progress to date (%)
Construction of bulk link line from 4 Boreholes to 7ML Reservoir in Olifantshoek: Phase 3 1 100 100
Dibeng Sewer Network, Phase 4 -797 stands 2 43 58
Construction of 142 BNG Houses in Siyathemba 3 10  
Dibeng Sewer Network, Phase 4 -797 stands 3 43 58

Table 2: Project Progress to date – May 2023

Project Name Project No. Current Progress to date (%) Expected Progress to date (%)
Construction of bulk link line from 4 Boreholes to 7ML Reservoir in Olifantshoek: Phase 3 1 5 0
Dibeng Sewer Network, Phase 4 -797 stands 2 25 80
Repair of existing storm water drainage in Welgelee and Ditloung villages 3 70 92

Completed Projects

Table 1: Key WSIG Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Construction of bulk link line from 4 Boreholes to 7ML Reservoir in Olifantshoek: Phase 3 WSIG Equipping of new four (4) boreholes.
Construction of pumping main pipeline (3615m) from four (4) boreholes to the storage reservoir.
Construction of pump houses for four (4) borehole pumps, including security features.
Electric supply for pumps
R 8 972 847.77 R 8 972 847.77 100 13 Project completed in 2023-24

Table 2: Key INEP Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
10 Electrical Reticulation and 40 Houses connections in Rooiwal OWN FUNDS Construction of electrical bulk line and connection of 40 households to the electrical grid R 1 975 074.90 R 1 960 827.04 100 6 Project completed in 2024-25

Table 3: Key HSDG Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Construction of 142 BNG Houses in Siyathemba HSDG Construction of 142 low-cost housing in Siyathemba  R 25,771 ,249 .30 R 2 242 098.69 10  

Foundation – 17

Wall Plate – 10

Table 4: Key MIG Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Dibeng Sewer Network Phase 4 – 797 Stands MIG + KUMBA SLP + OWN FUNDS Connections of 8488m of sewer pipeline, 185 Manholes, Connection of 500 household’s toilets to the sewer network R 34 345 349.75 R33 760 424.83 100 26 Project completed in 2024-25
2 Upgrading of Sports field in Dibeng MIG + OWN FUNDS Grassed Soccer & Rugby field with athletics track
Renovating the existing changing room, ablutions, and kitchen
Refurbishment of the two Mini-courts
R 15 179 497.73 R 15 179 497.73 100 11 Project at Practical Completion stage

Table 5: Key Own Funding Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Electrical Reticulation and 40 Houses connections in Rooiwal OWN FUNDS Construction of electrical bulk line and connection of 40 households to the electrical grid R 1 975 074.90 R 1 960 827.04 100 6 Project completed in 2024-25

Table 6: Key SLP’s Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Refurbishment of the Old Kathu Waste Water Treatment Works KUMBA SLP Replace mechanical screens and inlet works, Refurbish Control room wiring, lighting, pumps, etc, Replace grit separator pumps and motors, ,Replace mechanical pumps at basins of the reactors, Repair and replace clarifiers components not working, Maintenance of existing valves and pumps at the plant, Refurbish and upgrading of sludge drying beds, Repair manholes, Service, repair and replace biological reactor components R 5 750 000.00 R 5 750 000.00 100 7 Project completed in 2023-24
2 Resurfacing of Kathu internal roads KUMBA SLP Asphalt resurfacing of Frkkei Meter street (710m dual carriage-way), Ben Alberts Street (1420m dual carriage-way) and Kareelaan street (750m single carriage-way) R 30 000 000.00 R 26,496,509.97 26 N/A Project completed in 2023-24
3 Upgrading of Reservoir Pumpstation in Mapoteng KUMBA SLP Pumpstation building refurbishment
Supply and install one duty duty and one standby pump/motor combination
Supply and install motor control centre panel including all cabling, protection ans switchgear
Security fencing including flood lights
R 3 450 000,.00 R 3 450 000,.00 100 7 Project completed in 2023-24

Table 7: Key SLP’s, Own Funding and INEP Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Upgrading of a section of Sewer reticulation in Mapoteng KUMBA SLP + OWN FUNDS Connections of 2400m of sewer pipeline, 47 Manholes, Clearing of blocked existing sewer lines, Refurbishment of EX6 Sewer pumpstation, changeover of water pipe of Asbestosis pipes to uPVC, upgrade of road to paved road R 25 949 749.38 R 25 949 731.30 100 26 Project completed in 2024-25
2 Dibeng Sewer Network Phase 4 – 797 Stands MIG + KUMBA SLP + OWN FUNDS Connections of 8488m of sewer pipeline, 185 Manholes, Connection of 500 households toilets to the sewer network R 34 345 349.75 R 33 760 424.83 100 26 Project completed in 2024-25
3 New Electrical Reticulation and 146 House connections Ext Ph 2 INEP + OWN FUNDS Construction of electrical bulk line and connection of 174 households to the electrical grid R 6 349 749.52 R 6 345 277.71 100 11 Project completed in 2024-25
4 Upgrading of Sports field in Dibeng MIG + OWN FUNDS Grassed Soccer & Rugby field with athletics track
Renovating the existing changing room, ablutions, and kitchen
Refurbishment of the two Mini-courts
R 15 179 497.73 R 15 179 497.73 100 11 Project at Practical Completion stage

Ongoing Projects

Table 1: Key WSIG Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Dibeng Bulk-Water Augmentation, Equipping Of Boreholes  and its Ancillary works WSIG Equipping of 1 x existing and  3 x new boreholes, pumps, rising mains, 4 x tank refurbishments R 18 093 015.76 R 11 840 349.87 66 13 Project Stopped by Land owner – Municipality applied for servitude expropriation
2 Upgrading of Dibeng Bulk Water Infrastructure Phase 1 WSIG Drill and Equip 4 x new boreholes, refurbish 2 x exisitng boreholes, pumps, rising mains, tank refurbishments R 25 072 100.00 R 12 428 108.93 50.7 10 Project prgressing well

Table 2: Key MIG Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Dibeng Sewer Phase 5 – 529 stands MIG Sewer reticulation & household connections R 22 825 811.36 R 15 273 864.22 89,0% 16 Project progressing well
2 Upgrading of Sports field in Dibeng MIG + OWN FUNDS Grassed Soccer & Rugby field with athletics track
Renovating the existing changing room, ablutions, and kitchen
Refurbishment of the two Mini-courts
R 15 179 497.73 R 13 351 830.72 99,0% 11 Project at Practical Completion stage
3 Olifantshoek Water Reticulation 1300 stands MIG Internal reticulation & yard connections R 27 890 930.09 R 2 483 006.57 0,0% N/A Project at Design and Procurement stage

Table 3: Key SLP’s Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
1 Olifantshoek Internal Road Upgrade KHUMANI SLP The construction of 1,3km paved road R 17 250 000.00 R 686 550.00 20,0% N/A Jood street (285m) completed
2 Installation of Streetlights in Dibeng, Babatas and Olifantshoek KHUMANI SLP Supply and Installation of 2 High Mast Lights in Dibeng.
Supply and Installation of 2 High Mast Lights in Babatas.
Supply and Installation of 3 High Mast Lights in Olifantshoek
R   8 877 816.00 R 423 122.00 5,0% 10 Busy with assembling the lights structure, trenches excavated
3 Gamagara Water Programme KHUMANI SLP The scoping, feasibility study, design and implementation of a strategy to resolve the water challenges within Gamagara LM R 19 550 000.00 R 410 812.00 100,0% N/A Project at Design and Procurement stage
4 Gamagara Waste Management Project: Landfill construction Phase 1 KHUMANI SLP Detailed design,
EIA & Waste License
Water use License,
Subdivision & Subsequent Rezoning
R 17 250 000.00 R 2 835 159.70 0,0% N/A Project at Design and Public Participation
5 Light-scale industrial business hub – (Olifantshoek) KHUMANI SLP Design and Construction of Olifantshoek Light Scale Industrial Business Hub R 11 500 000.00 R- 0,0% N/A Project at Design and Procurement Stage

Table 4: Key SLP’s Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
6 Special Needs Education Centre in Kathu KHUMANI SLP Construction of Special needs Education centre in Kathu R 3 694 375.00 R- 0,0% N/A Project on hold for finalization of the implementation methodology
7 Construction of Reservoir in Dibeng AFRIMAT SLP Design and Construction of 700KL elevated Steel tank R 11 500 000.00 R- 0,0% N/A Project at Design and Procurement stage

Table 5: Key SLP’s Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
8 Construction of Toilet structures in Dibeng TSHIPI E NTLE Construction of 197 structures and connection of the households to the water and sewer networks in Dibeng R 5 192 621.78 R 1 974 561.45 55,0% N/A Project progressing well
16 Installation of Chlorination facility at Mapoteng reservoir SOUTH32 Installation of the Chlorination system at Mapoteng reservoir. R   1 029 610.00 R   1 029 610.00 100,0% N/A Project Completed
17 Refurbishment of borehole KM14 in Mapoteng SOUTH33 Refurbishment of borehole in Mapoteng R-   0,0% N/A Project at Concept stage

Table 6: Key Own Funding Project Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
7 Electrical Reticulation and 96 Houses connections in Rooiwal OWN FUNDS LV network & household connections R 4 800 000.00 R- 0,0% 0 Site establishment

Table 7: Key EPWP-IG Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
18 Water Meter Programme Phase 3 – Installation of Water meters EPWP-IG Water Meter installation or repair R 689 000,00 R 352 934,00 N/A 26 Programme progressing well
19 Cleaning of Waste Disposals (Landfill) in Dibeng EPWP-IG Cleaning of the areas surrounding the landfill in Dibeng R 689 000,00 R 57 378,10 N/A 13 Programme progressing well

Table 8: Key HSDG Status

No Project Name Funder Scope Budget Actual Expenditure Progress (%) Job Creation Remarks
20 Construction of 142 BNG Houses in Siyathemba HSDG Construction of 142 low-cost housing in Siyathemba R 25 771 249.00

R 2 242 098.69

10,0% N/A 10 houses Completed

Sishen Five Year LED Programme 2022 – 2026

  Project Community Project Phase Consultant   Status
  Community Development          
  Gamagara Municipality          
  Education and Skills          
  Bursary Programme JT Gaetsewe Implementation      
  Construction of ECD Centers Mapoteng, Dibeng Concept      
  Youth Service Centers Kathu Concept      
  Health          
  Establish a level 1 casualty facility Kathu Concept      
  Infrastructure Projects          
  Sanitaion Community Project Phase Consultant Status % Status
1 Construction of internal sewer network 797 households (Phase4) Dibeng Implementation Civil Sense Consultant Engineering Construction stage 43 %

Setting out 50%-Excavations Soft

46%-Excavations Rock

51%-Pipe Work

40% -Manholes 37%

2 Refurbishment of old plant 3.5 ML Kathu Wastewater Treatment Works Kathu Implementation Agisa Consulting Engineers Construction stage 99 % Works completed, busy with snuglist
3 Construction of gravity flow Sewer network to eliminate Mapoteng sewer pump station Mapoteng Implementation Tsela Tsweu Consulting Engineers Construction stage 99 % Busy with excavation of trenches, drilling and blasting
4 Upgrading of Sewer pumpstations Mapoteng Feasibility Tsela Tsweu Consultant Engineers Planning stage  50%

Technical report was submited .The cashflow of the project was submited but the next year

5 Replacement of existing manhole covers with lockable manholes Kathu Feasibility Municipality will do internal program   Project cancelled by Kumba
  Water Community Project Phase Consultant   Status
6 Construction of 2×4.5 ML Reservoirs and 1.8 ML Elevated tower Sishen / Mapoteng Feasibility IX Engineering Planning stage 80% Technical Report to be submitted to DWS on the 07th of December for Comments
7 Refurbish Mapoteng Reservoir Mapoteng Implementation Tesela Tsweu Consultant Engineering Construction stage 43 % Technical report was submitted and the cashflow of the project was submitted.
  Electric Community Project Phase Consultant   Status
8 Refurbishment and Upgrade of Industrial Substation Kathu Feasibility HVR Consulting Engineer Planning stage 10 % The Consulting appointment was done on Risk. Technical report was submitted. The technical department wait for the data base for consultants.
9

Construction of New 10 MVA Substation in Olifantshoek

Olifantshoek Feasibility MVM Africa Consulted   The project is on hold
15 Resealing of Roads in Kathu Kathu Feasibility + Construction  R&G Kalahari Consulting Engineers   The Kumba Mine has appointed a consultant. Assessment Report for the improvement and rehabilitation of Roads in Kathu was submit. The letter Kumba Mine was submitted
16 Resealing of Roads in Dibeng Dibeng Feasibility + Construction  no consultant   no progress
17 Reseal 3.6 km of Frikkie Meyer Road Kathu Feasibility + Construction  no consultant   no progress
19 Resealing of 1.9km Ian Flemming Road Kathu Feasibility + Construction  no consultant   no progress

Khumani Five Year LED Programme 2022 – 20226

  Infrastructure Projects        
  Community Development R 3,212,500.00 Community Status % Remarks
1 Special Needs Education Centre in Kathu Gamagara R 3,212,500.00 Ward 1,6 and 7 Planning Stage The location for construction not yet defined
  Enterprise Development        
2 Light-scale industrial business hub R 10,000,000.00 Ward 3 and 4 Planning Stage Brief meeting with the 4 nominated consultants held on the 06th November 2023
  Water R 17,000,000.00 Community Status % Remarks
3 Gamagara Water Programme R 17,000,000.00 All Wards Planning Stage Brief meeting with the 4 nominated consultants held on the 06th November 2023
  Electrical R 5,000,000.00 Community Status % Remarks
3 Installation of streetlights in Dibeng, Babatas, and Olifantshoek R 5,000,000.00 Dibeng / Olifantshoek & Babatas Planning Stage Brief meeting with the 4 nominated consultants held on the 06th November 2023
  Road and Stormwater R 15,000,000.00 Community Status % Remarks
4 Olifantshoek internal roads upgrade R 15,000,000.00 Olifantshoek Planning Stage Brief meeting with the 4 nominated consultants held on the 06th November 2023
  Waste Managemt R 15,000,000 Community Status % Remarks
5 Gamagara Waste Management Project: Landfill Construction (Phase 1) R 15,000,000.00 All Wards Planning Stage Waste management plan approved by Council

Challenges and Mitigation

The municipality is proactively addressing challenges to ensure project success:

  • Funding for 529 toilet structures in Dibeng is being secured.
  • Land access issues for the Dibeng Bulk Water project are being resolved through engagement with the Department of Water and Sanitation and land expropriation processes.
  • Community unrest impacting project timelines is being managed through continuous dialogue and engagement.

Project Photos and Maps

Visual updates on project progress are provided below for public information.